Supreme Court Restores Arbitral Award for Dredging Contractor, Sets Aside Division Bench Order That Had Halved It

Supreme Court Restores Arbitral Award for Dredging Contractor, Sets Aside Division Bench Order That Had Halved It

Judgment
November 22, 2026Supreme Court of India

On 18 November 2026, a Supreme Court Bench of Justice J. B. Pardiwala and Justice K. Vinod Chandran set aside a Division Bench judgment that had halved an arbitral award in favour of a dredging contractor and restored the award, in M/s. Marino Dredgeco Ltd. v. The Board of Trustees of the Port of Kolkata (2026 INSC 1238, Civil Appeal Nos. 14303 and 14304 of 2026). Justice Chandran authored the judgment. This item is based on the published text of the judgment. The amount of the restored award, any payment date and costs are not stated in it.

What Happened

The Court allowed the contractor's appeal and disposed of the Port Trust's appeal, which had sought to set aside the whole award. It set aside the Division Bench's judgment under Section 37 of the Arbitration and Conciliation Act, 1996, and restored the arbitrator's award of 3 November 2003.

Background: The Dredging Work and the Award

The contractor had been engaged to dredge a channel and basin at Sagar Island. The original contract was paid in full, apart from a small balance of Rs 2,79,32,865 out of Rs 2,86,56,200. The Port Trust ordered additional re-dredging by a letter of 19 July 2000, and the contractor claimed payment for that work. The arbitrator made an award, and a Single Judge under Section 34 affirmed it. The Division Bench then halved the amount payable and reduced interest to 6 percent from 8 February 2002, reasoning that the additional claim exceeded 70 percent of the original contract value and shocked the conscience of the Court.

The Legal Question Explained: The Limits of Section 37

A challenge to an award under Section 34 can be made only on narrow grounds, and an appeal under Section 37 is narrower still. The question here was whether a Section 37 court could reduce an award by half on the footing that it shocked the conscience. The Court considered cases including Gayatri Balasamy v. ISG Novasoft Technologies (2025 INSC 605), Ssangyong Engineering v. National Highways Authority of India, Somdatt Builders v. National Highways Authority of India and Pam Developments v. State of West Bengal.

What the Court Said

The Court noted that the Division Bench had itself found that the award was not based on no evidence and was not perverse. The award rested on joint measurements and on levels recorded before and after the work. A completion certificate was not needed for payment. Reducing the award because the additional claim exceeded 70 percent of the original contract was a subjective judgment that ignored the nature of the work, and the fact that the Port Trust is a government body did not justify leniency. The award could not be divided into valid and invalid parts, because the measurements and invoices were of a single character. The Court held that Batliboi Environmental Engineers v. Hindustan Petroleum Corporation, which concerned damages and not invoices, did not apply.

Why It Matters

The ruling reinforces the narrow scope of review of arbitral awards, including by appellate courts. It says that the size of a claim, compared with the original contract, is not by itself a ground to cut an award, and that an award based on measurements and records is hard to disturb.

For public sector bodies in contracts with private contractors, it signals that arguments against an award must identify a legal ground and not rest on fairness alone.

What Comes Next

With the award restored, the contractor can seek its enforcement, and the Port Trust has no further appeal on this point in the ordinary course. The judgment does not state the restored amount or a payment schedule, so the next steps will depend on the award itself and on any execution proceedings.

Source: Supreme Court of India