Supreme Court Restores Arbitral Award in Port Dredging Dispute, Holding That a Section 37 Court Cannot Halve It Because It Shocks the Conscience
On 18 November 2026, a Supreme Court Bench of Justice J. B. Pardiwala and Justice K. Vinod Chandran decided M/s. Marino Dredgeco Ltd. v. The Board of Trustees of the Port of Kolkata (2026 INSC 1238, Civil Appeal Nos. 14303 and 14304 of 2026). Justice Chandran authored the judgment. The Court set aside a Division Bench order that had reduced an arbitral award by half, restored the award, and held that a court hearing an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 cannot cut an award merely because the claim looks large. The account rests on the published text of the judgment. Here is the story, the legal reasoning, and what it means for you.
A Dredging Contract and a Claim for Extra Work
The contractor was engaged to dredge a channel and basin at Sagar Island. The original contract was paid for in full, apart from a small balance. The Port Trust then ordered additional re-dredging by a letter dated 19 July 2000, and the contractor claimed payment for that further work. The dispute went to arbitration, and the arbitrator's award is dated 3 November 2003.
A Single Judge under Section 34 of the Act affirmed the award. In an appeal under Section 37, a Division Bench halved the amount payable and cut the interest to 6 percent from 8 February 2002. Its reason was that the additional claim exceeded 70 percent of the original contract value and shocked the conscience of the Court.
The Legal Concept: How Far Can a Court Interfere With an Award?
Arbitration is meant to be final. A party can challenge an award under Section 34 only on limited grounds, such as the award conflicting with the public policy of India or suffering from patent illegality. An appeal under Section 37 is narrower still, because the appellate court looks at whether the Section 34 court exercised its powers properly. It is not a second look at the merits.
The Court referred to Gayatri Balasamy v. ISG Novasoft Technologies (2025 INSC 605), Ssangyong Engineering and Construction v. National Highways Authority of India, Somdatt Builders NCC NEC (JV) v. National Highways Authority of India and Pam Developments v. State of West Bengal.
What the Court Decided
The Court noted that the Division Bench had itself found that the award was not based on no evidence and was not perverse. The award rested on joint measurements and on levels recorded before and after the work. The lack of a completion certificate did not bar payment. A reduction made only because the claim exceeded 70 percent of the original contract value was, in the Court's view, a subjective judgment that ignored the nature of the work, and a contract with a government body gives no ground for leniency.
The Court also held that the award could not be split into valid and invalid parts, since the measurements and invoices were of one character. It distinguished Batliboi Environmental Engineers v. Hindustan Petroleum Corporation, which concerned damages and not invoices.
The Division Bench judgment was set aside, the contractor's appeal was allowed and the award was restored. The Port Trust's appeal, which sought to set aside the whole award, was disposed of. The judgment does not state the restored amount, a payment date or costs.
What It Means in Practice
For contractors, the decision is a reminder that a well-supported award based on measurements and records will be hard to dislodge, and that the size of a claim is not itself a ground for challenge.
For public bodies, it signals that an award cannot be cut on the footing of fairness alone. Arguments in a Section 34 or Section 37 proceeding must identify a legal ground.
For lawyers, it shows that the line between the courts' narrow review and a re-examination of the merits is firmly drawn, and that a party seeking to modify an award needs a basis in the Act and in the cases.
The Indian Angle
Delay is the recurring theme. An award of November 2003 was still being contested before the Supreme Court in 2026. Arbitration in India has been strengthened by amendments and judicial restraint, but the case shows how long an award can take to become final. Parties should pay close attention to the record before the arbitrator, since that record is likely to decide the outcome.