He Paid Rs 51 Lakh, the Bank Paid the Rest, and the Flat Never Came. Who Gets the Refund? The Supreme Court Drew the Line.
In Madhu Kudapa (formerly K. Madhusudhan Rao) v. M/s Lodha Healthy Constructions and Developer Pvt. Ltd. and Another (Civil Appeal No. 8994 of 2022 with Civil Appeal Nos. 4622-4623 of 2023), decided on 15 October 2026, a bench of Justice P.S. Narasimha and Justice Alok Aradhe, with Justice Aradhe writing the judgment, held that a homebuyer whose flat was never delivered can be refunded only the money he actually paid from his own pocket, with 12 per cent simple interest, and not the loan amount the bank paid directly to the builder. The Court also refused rent on top of interest, awarded Rs 15 lakh as lump sum compensation, and upheld a finding that the bank had been deficient in service. Here is the story of a delayed project, a tripartite loan agreement, and the principle of unjust enrichment that decided the case.
A Booking in 2009 and Thirteen Tranches
The builder launched a residential project at Kukatpally in Hyderabad in 2009. On 8 August 2009, the buyer, then a non-resident Indian, booked a flat priced at Rs 2,30,73,876 and paid Rs 51,11,576 from his own funds, about 22 per cent. A bank sanctioned a loan of Rs 2 crore, and a tripartite agreement among the buyer, the builder and the bank was signed on 30 January 2010. Between February 2010 and July 2011, the bank released Rs 1,68,80,531 to the builder in thirteen tranches, so that about 95 per cent of the price had gone to the builder by the time possession fell due. The flat was never delivered. The buyer went to the National Consumer Disputes Redressal Commission in May 2013, seeking a refund of Rs 2,19,92,107 with interest, rent and compensation. The bank recalled the loan in January 2015 and sued him for Rs 2,51,15,774, a suit that was dismissed on 10 December 2024 and is under appeal in the High Court.
What the Commission Ordered
The Commission held the builder liable and rejected its force majeure plea. It ordered a refund of the entire deposit with 9 per cent interest, found the bank deficient in service because it had no evidence of verifying construction before releasing the money, and awarded Rs 2 lakh against it. It did not decide the claims for rent and compensation. The builder did not appeal and deposited Rs 4,43,24,510 with the Commission. The buyer appealed on rent, compensation and interest, and the bank appealed against the finding of deficiency and the order for a full refund.
Refund of Own Money Only
Applying the principles of unjust enrichment under Sections 64, 65, 70 and 72 of the Indian Contract Act, 1872, the Court held that although the builder's retention of the money was unjust, the refund could go only to the buyer's own payments. These were Rs 51,11,576 paid to the builder and Rs 76,23,150 paid to the bank towards the loan, a total of Rs 1,27,34,726. The fiction in the tripartite agreement that the loan money was deemed to be disbursed to the buyer does not make unpaid loan money his own. Refunding the full sum would have enriched him unjustly, since the loan remained a debt owed to the bank.
Interest, Rent and Compensation
The Court awarded interest at 12 per cent simple per annum from the date of each payment, and not the 18 per cent the buyer sought, because the agreement fixed 12 per cent for default in possession and a departure from the contract needs strong reasons. It rejected the claim for rent on five grounds. The Consumer Protection Act has no rent control style provision, rent on top of interest would compensate twice, rent had not been pleaded or proved, the buyer had elected the refund remedy, and his own letter of 2012 contradicted the claim. In its place, the Court awarded a lump sum of Rs 15 lakh for rent, mental agony, harassment and litigation costs, in full settlement against the builder.
The Bank Was Deficient
The buyer had met his initial burden by repeatedly asking the bank to verify construction and by showing the bank's own report that the building was only 90 per cent complete on 30 October 2012. The burden then shifted to the bank, which produced no inspection reports. Paying tranches that matched the builder's demands showed only that it paid what was asked, and not that it verified construction stages as its sanction letter required. The deficiency finding and the Rs 2 lakh compensation were upheld. The Court directed the Commission to release Rs 1,27,34,726 with interest and Rs 15 lakh from the builder's deposit, and kept the balance in an interest-bearing account pending the bank's appeal, whose merits the High Court will decide without being influenced by this ruling.
What This Means for Homebuyers, Banks and Builders
For homebuyers with a loan, the ruling sets a clear expectation. A refund will track what you actually paid, including what you repaid to the bank, and the rest of the loan is a matter between the bank and the builder. Choose a refund or possession with compensation deliberately, because claiming both rent and interest is unlikely to succeed. For banks, it is a warning that releasing construction-linked tranches without verifying progress can amount to deficiency in service. For builders, it confirms that contractual interest rates for default will generally be the benchmark. For lawyers, keep the tripartite agreement and payment records at the centre of every refund claim.
This blog is for general informational purposes and does not constitute legal advice. For guidance on property purchases, delayed possession or consumer claims, please contact our team.